The LiFePO4 Battery Isolation Manager (BIM) monitors voltage and connects batteries when needed. Under normal charging conditions, the BIM will connect for 15 minutes every 35 minutes. That means that the BIM will connect for 15 minutes, disconnect for 20 minutes, and repeat this cycle until the coach battery is charged.
Ask a technical specialist now at 855.292.2831
If the coach battery resting voltage exceeds 13.4 V then the BIM will disconnect. A resting voltage greater than 13.4 V indicates a fully charged battery. Note that “resting voltage” means that no current is flowing to the coach battery.
The BIM will disconnect if the alternator voltage exceeds 14.4 V. This protects the coach battery from overcharging. The LiFePO4 Battery Isolation Manager will disconnect if the voltage difference between the alternator and the coach battery is less than 0.1 V. If the voltage difference is too low, then there is a negligible charging current, and no need to connect to the coach battery.
The BIM will disconnect if the alternator voltage drops below 13.3 V. If the alternator voltage is too low, then it cannot adequately charge the coach battery, so there is no reason to connect.
Dimensions: (3″W x 5-1/4″ H x 2″D)
Copyright © 2024 Dragonfly Energy. All rights reserved. Dragonfly Energy collects personal information for its internal use. We do not share customer information with any third parties.